When the lithium market shifted, a mining leadership team needed to make decisions fast.

Industry
Lithium mining
Role
Integration Lead
Engagement
4-month contract

Two unresolved strategic questions. A dispersed team under pressure. No time for cleaner data. Two workshops were facilitated, and both decisions were made in the room.

"We achieved the outcomes – to align the team and pivot thinking towards large discoveries."
Pierre Malan, Executive General Manager, Exploration & Development

Core Lithium

2 days

To align the exploration team around a new strategic direction.

1 day

To agree mine sequencing across an entire province.

$1B+

Revenue pipeline confirmed and de-risked.

Challenge

Two decisions. Neither moving.

The lithium market shifted fast. The exploration team was dispersed across states, operating under pressure as two questions remained unresolved: which direction should exploration go, and in what order should mines across the province be developed?



Precision in mining matters, but waiting for cleaner data and greater certainty wasn’t an option. The team needed to move now.

Approach

Finding the decision hiding inside the complexity.

The experts had most of what they needed. What was missing was a way to see it all at once: the constraints, the assumptions, the dependencies. At the sharp end of a 4-month engagement, I designed two workshops to help make the choices visible.

2 day workshop
Pivoting the exploration strategy


The team hadn't had space to process the external context together, let alone agree on a response to it. This workshop created that space deliberately.

  • Rich pictures to surface how each part of the team saw the organisation's current position
  • Structured review of the external environment to build shared understanding across states
  • Reverse brainstorming to stress-test assumptions and challenge existing strategy
  • Bottom-up and top-down strategy using a business model canvas and 'postcard from the future'
  • Convergence on a strategic pivot and a concrete action plan

1 day workshop
Sequencing mines across a province


Mining engineers work with precise data. Here, that instinct had become the blocker. A large-format mud map was built in the room to surface geographical constraints and opportunities across the province. A shared assumptions table did the rest, becoming the key to the sequencing decision.

  • Mud map of the province: rivers, heritage sites, haulage routes made visible at once
  • Directionally correct assumptions on ore bodies, timelines, infrastructure and constraints captured in a simple table
  • Fast calculation of lead times and mine life stages from shared assumptions
  • Pragmatic sequencing agreed, with approvals risk assessed and resolved
results

Both decisions made. Both in the room

Exploration strategy reset

Leadership aligned around a pivot towards larger deposits — a conclusion they reached themselves.

Action plans, not open questions

Leadership aligned around a pivot towards larger deposits — a conclusion they reached themselves.

Exploration strategy reset

Both workshops closed with clear ownership and next steps. Nothing deferred offline.

Approvals confirmed as non-bottleneck

A major source of executive uncertainty about the province timeline - gone.

$1B+ revenue pipeline unlocked

Sequencing confirmed, approvals de-risked. The board committed to province-wide development.

"Aligned the team and pivoted thinking."
“You did a great job facilitating under difficult circumstances where we had to take the team through the change process at the same time. We achieved the desired outcomes - to align the team and pivot thinking towards large discoveries and prioritised study focus “
Pierre Malon
Executive general manager, exploration and development
Core Lithium

Looking for clarity in transformation or delivery?

Let’s talk about where things are stuck, what decisions need to move, and how to create momentum.

Talk with Rebecca
Smiling woman in red sweater holding a coffee cup sitting at a blue table inside a cafe.

You might find these case studies relevant

When a multi-million dollar copper mining programme in the DRC stalled before it started, the foundation had to come first.

Seven payment milestones locked before the team left for site.

Read the case study